May 27, 2008
Summer Roadway Paving
Gleneagles Country Club
Roadway Paving will begin May 27 and continue through August 21
TO PRINT THIS DOCUMENT CLICK "print" BUTTON AT BOTTOM OF PAGE

Large machinery and workmen will be on site. This requires all members to ensure that your property is secured. If you have a vehicle parked during the period your roadway and parking lot are to be resurfaced, make sure a friend or neighbor has a key to your vehicle if you are not presently on property, and that your association knows who that person is. Please cooperate to prevent your vehicle from being towed at your expense.  

Roadway Paving Schedule *
May 27-30
Mobilization

June 2-8 finished 6/10/08
Midrise, Glen Garry Lane, Dundee Lane, Lomond Hills Trail

June 9-20 finished 6/28/08

Loch Maree

June 23-July 2 finished
Victory Lane Condo Association, Loch Katrine 

July 7-10 finisshed
Clunie

July 11-21
prepared needs paving Strathearn  

July 22-28
Glendevon
Drainage 75% complete -- working GREAT

July 29 - August 7 finished
Main Club, Victory Lane, Tennis Center


August 8-21
mostly prepared Legends Way
* Schedule is subject to change due to weather or other unforeseen circumstances.